The strengths identified most often in the TRP comments were as follows:
1. The narrative description of the programme was inadequate. There was insufficient, unclear or questionable information on one or more of the following: the rationale, the strategic approach, the objectives, the activities, the indicators, the targets and the expected outcomes.
2. The budget information was inaccurate, questionable and/or not sufficiently detailed.
3. The proposal did not demonstrate complementarity or additionality; it was not clear how the programme related or added to existing programmes, including programmes funded by the Global Fund through earlier grants.
4. The proposal did not contain a good situational (i.e., gap) analysis.
Other weaknesses identified frequently were as follows:
5. Some of the proposed approaches or activities were inappropriate.
6. There were problems concerning the PR(s) or the SR(s).
7. The various sections of the proposal were not well aligned.
8. The M&E plan was inadequate.
9. The programme was too ambitious; some or all of the goals, objectives and targets were not realistic.
10. The use of partners (including NGOs) in the implementation of the programme was inadequate or unclear.
11. The programme did not focus sufficiently on vulnerable groups.
12. The plan for procurement and supply chain management was inadequate.
13. The proposal failed to adequately address issues of capacity building and technical assistance.
14. The proposal failed to address weaknesses identified by the TRP for proposals submitted in earlier rounds of funding.
15. Insufficient attention was paid to human rights issues.
16. The budget (and therefore the programme) was imbalanced; too much or too little was allocated to one or more sectors or activities.
17. There were problems with the structure or functioning of the CCM.
18. The proposal did not adequately explain the roles and responsibilities of the various players.
19. The proposal development process was not sufficiently transparent or inclusive.
20. The proposal demonstrated insufficient co-funding.
21. In HIV/AIDS and TB proposals, there were either no joint activities or insufficient joint activities involving both diseases; or the information on joint activities was incomplete.
22. The treatment, care and support component of the proposal was missing or inadequate.
23. The proposal failed to demonstrate absorptive capacity.
24. Information on sustainability was lacking.
25. How health systems will be strengthened was not well explained.
26. There was a lack of information in the proposal concerning problems with previous Global Fund grants.
27. The proposal failed to make the case for additional funding over and above that received from earlier grants.
28. There was insufficient information on how the project would be coordinated.
"The Aidspan Guide to Round 7 Applications to the Global Fund"discusses all of these in detail, and provides links to proposals and TRP comments that provide illustrations of the strengths.