ABSTRACT This long article deals with the Office of the Inspector General’s audit report on the Global Fund grants to Kenya. It is a worrisome report revealing an ineffective procurement and supply chain system and a government failing to meet its co-financing commitment. It is also of concern that, at the present rate of progress, the Agreed Management Actions will take too long to remedy the situation for the current grants. This article is a wake-up call.
On 11 March 2022 the Office of the Inspector General (OIG) published its audit report on the Global Fund Grants in Kenya.
According to the report, the Global Fund had approved $1.8 billion and disbursed over $1.4 billion to Kenya.
One and a half million people are living with HIV of which 96% knew their status, 89% were on treatment and 94% were virally suppressed in 2020. Annual new infections decreased by 44% from 75,000 in 2010 to 41,416 in 2019 and AIDS-related deaths decreased by 59% from 51,000 in 2010 to 20,997 in 2019.
In 2020, 4.5 million malaria cases were treated but, due to travel related and other pandemic disruptions, only 194,000 long-lasting insecticidal nets (LLINs) were distributed in 2020 against a target of 12.9 million.
Kenya is among the 30 global high TB and TB/HIV burden countries. In 2021, it transitioned out of the 30 high MDR/RR-TB burden countries. The 2016 TB prevalence survey estimated TB incidence to be 426 cases per 100,000 persons, TB case notifications decreased by 14% from 81,518 in 2015 to 70,387 in 2020, and between 2018 and 2020 the TB incidence rate fell by 11% from 292 to 259 cases per 100,000 population. The TB treatment success rate was 84% for new cases in 2018.
The audit's overall objective was to provide reasonable assurance on the adequacy, effectiveness, and efficiency of Global Fund grants to the Republic of Kenya. Specifically, the audit assessed:
Objective |
Rating |
Scope |
| Controls and assurance over the procurement and supply chain management systems are sound to deliver and account for quality-assured medicines and health products. | Ineffective | Audit Period:January 2018 to April 2021
Grants and implementers:NMF2 grants implemented by the National Treasury, Kenya Red Cross Society (KRCS) and Amref (formerly called the African Medical and Research Foundation)
Scope exclusion:None
|
| Effectiveness of Global Fund COVID-19 response in maintaining and scaling up TB and HIV screening and testing and LLINs intervention, including adaptation during the COVID-19 period. | Partially Effective | |
| Effectiveness of the financial assurance framework/mechanism during the pandemic including absorption capacity, C19RM funding utilization and co-financing mechanism. | Needs significant improvement |
The report notes four areas of achievement/good practice:
The report raises the following key issues:
The report notes that, since March 2020, the Government has taken stringent containment measures to slow the spread of the virus, including lockdowns and dusk-to-dawn curfews. However, no further information on the impact is given.
The National Treasury, KRCS and Amref Health Africa are grant PRs. The MOH implements grants on behalf of the National Treasury through the national programs for the three diseases. Each disease program is implemented by a government implementer and a non-governmental organization (NGO).
Approximately 60% of grant funding goes towards procuring medicines and health products. The National Treasury contracted KEMSA, a government entity, as its procurement agent for the grants. KEMSA is responsible for procuring, storing, and distributing medicines and health products.
Kenya has received $45 million through C19RM and grant flexibilities to fight COVID-19’s impact on the three diseases. These amounts are included in the grants presented above totalling $444.2 million.
The report has five findings.
.
KEMSA is procuring quality-assured health commodities at competitive prices; however, insufficient coordination and procurement planning among stakeholders creates inefficiencies and bottlenecks, delaying their availability; and the audit noted irregularities in procurements, weak contract management, and inadequate assessment of vendor performance:
Delayed procurement processes and inadequate procurement plans have led to sub-optimal budget absorption rates for the malaria program (74% at the end of the grant) and for COVID-19 funding (51% at the end of the grant).
:
.
Ineffective controls at KEMSA’s warehousing and distribution systems are affecting commodity traceability, and accountability for commodities received and distributed cannot be ensured. There is no robust system to monitor, track and report commodities delivered to HFs, and HFs cannot fully account for the drugs that they have received. The audit noted ineffective controls across the supply chain at all levels, which seriously compromise the achievement of grant objectives. These are detailed in full in the main report.
:
:
There was limited risk assessment and ineffective risk monitoring for procurement and supply chain risks in Kenya. Kenya did not benefit from a full Country Portfolio Review in 2020 or 2021, despite procurement and supply chain risk levels having increased significantly between 2019 and 2021. The increased risk was due to several factors, such as declining performance following a change of Chief Executive Officer at KEMSA, and widely reported corruption allegations over KEMSA’s personal protective equipment procurements. The Secretariat performed a risk assessment for the Kenya portfolio, adjusting the ratings upwards: Procurement risk moved to High, and In-Country Supply Chain risk to Very High. On 13 April 2021, during the grant making stage, this assessment was documented in the Integrated Risk Management module which records all grant-related risks:
RISK CATEGORY |
2019 CPRASSESSED RISK LEVEL |
2020ASSESSED RISK LEVEL |
2021 REVIEWASSESSED RISK LEVEL |
Procurement |
Moderate |
No assessment performed in 2020 |
High |
In-country supply chain |
Low |
Very High |
:
.
COVID-19 severely impacted Global Fund Programs in Kenya during 2020. While the programs managed to recover thanks to adaptations and reprogramming, further efforts will be needed if grants are to reach program targets by 2023. Also, several issues noted during the previous OIG audit in 2018 remain.
:
:
This report must raise concerns in the Secretariat. Look at the ratings in the previous OIG audit report on Kenya published in November 2018:
.
.
.
.
This audit report rates the effectiveness of the financial assurance framework/mechanism as
. More importantly, it rates the controls and assurance over the procurement and supply chain management systems to deliver and account for quality-assured medicines and health products to be
. So, grant performance has deteriorated, especially procurement and supply chain processes. This is clear from the second key issue in the report: “Inadequate supply chain controls have worsened”. It is therefore surprising that the report includes as the second achievement “Centralized supply chain arrangements under the Kenya Medical Supplies Authority (KEMSA) have …… enhanced both accountability and country ownership of the three programs and has created efficiencies for all three major funders” (Global Fund and the Kenyan and US governments). What efficiencies were created? KEMSA’s performance does not reflect any.
The third achievement listed in the report is that “Governance and supply chain challenges are being tackled by a newly constituted Reform Committee” and “A new five-member Board was appointed in April 2021, with a mandate to enhance efficiency and continue the reforms.” But, under the third finding, we are informed that “Key procurement risks had been highlighted by the assurance providers in 2019 but were not promptly escalated” and “at the instruction of the Global Fund, the LFA performed a review of procurement processes of health products undertaken by the PR (the National Treasury) through the KEMSA. The report was sent to the Global Fund in December 2019, and a Management Letter, with recommendations to mitigate the identified risks, was sent to the country in February 2020. The LFA review identified almost all the key procurement risks highlighted in this report, including long procurement processes and poor supplier performance. While proposed mitigations were sent to the country as part of the Management Letter, our audit noted no progress, and identified similar issues.” So, no progress was actually made.
From the many references in the report, KEMSA clearly remains a major problem. It is worrying that the so-called ‘KEMSA reform project’ has yielded no reported improvements.
On the day this audit report was published, the Global Fund Executive Director issued a statement about the report in which he said:
“The Global Fund had already responded to a decline in KEMSA’s performance due to deficiencies in the governance structures of the organization. Building on the joint Global Fund/USAID assessment of KEMSA in 2019 and recognizing the Kenya Office of the Auditor-General KEMSA audits, and the challenges at KEMSA following the 2020 corruption allegations, the Ministry of Health engaged with stakeholders, including partners, to form the KEMSA Reforms Implementation Committee (KRIC), which developed an action plan to address gaps in all the critical functions of the organization. Implementation of the KEMSA reforms action plan is ongoing under the leadership of the new KEMSA board and acting CEO, with support from the Global Fund and partners. The key objective of the KEMSA reforms is to address challenges in the national supply chain, specifically by establishing end-to-end visibility of health products and strengthening accountability and reporting at all levels of the supply chain.”
Sounds good; but it is still open-ended. And that was the frustration vented by civil society groups as reported by Devex on 29 March 2022. “This is a problem that has been there for a long time,” said Maureen Milanga, the director of international policy and advocacy for Health Global Access Project, speaking to Devex from Nairobi, Kenya. “The Global Fund should be held accountable because they keep funding a broken system.”
A respondent to the Devex article rightly pointed out that the Global Fund has a mandate to utilize existing in-country structures and work alongside in-country stakeholders (including civil society organizations (CSOs), government agencies, other donors) to strengthen them. But KEMSA’s performance has deteriorated. The Global Fund wants to raise more finance for health when here we have an in-country entity that is causing major cost inefficiencies with program consequences that go beyond finance. It may therefore be time for the Global Fund to revisit its policy on the use of local structures, and certainly this one.
It would be interesting to see what the current position is with the grants that closed at the end of June 2021. Unfortunately, at the time of writing this article, the data were not available from the Global Fund Data Explorer.
It is of concern that the Government failed to meet its co-financing commitments and that the audit report makes no mention of follow-up on this major issue. What is happening with regard to co-financing of the current grants that opened on 1 July 2021? They were in place at the time of the audit. So why is there no mention of the current grants? At the top of page 6 of the report it states: “Since 2003, the Global Fund has signed over $1.8 billion and disbursed over $1.4 billion to Kenya. Active grants total $444 million for the 2020-2022 Funding Allocation (July 2021 to June 2024 implementation period)”. This is confusing and probably best ignored because, according to the portfolio performance table in the report, the $444 million was the total of the grants that ended on 30 June 2021.
Given the poor performance and the evident urgent need to improve controls and cost effectiveness, it is surprising that AMAs 1 and 2 – for which 18 months and 21 months have been allowed – only require papers to be produced. When are the corrective actions going to happen? To get this portfolio back on track, some corrective actions should already have started, especially regarding the procurement and supply chain processes.
Virtually every OIG report includes the word ‘accountability’ but when do we see evidence of its application? Having worked in public sector governance for many years in many countries I have never seen anyone in a civil service or parastatal position held accountable for poor performance. And you can be sure that if a committee is appointed to oversee the implementation of any initiative/plan, apart from meetings, nothing is going to happen. So, it is not surprising that, as the Devex article shows, in their frustration at the lack of progress many CSOs in Kenya blame the Global Fund for not taking corrective action in the face of KEMSA’s repeated poor performance.
Finally, we at Aidspan reported on the poor performance of KEMSA and the governance issues that have dogged it in our article A looming shortage of antiretroviral drugs threatens the wellbeing of Kenyan citizens published in May last year. I hope that steps to mitigate and improve the situation will bear fruit sooner rather than later so that we are not writing about this these same issues in a year’s time!
No comments yet. Be the first to comment!