A success story: Global Fund grants in Burkina Faso show significantly increased absorption rates
GFO Issue 333

A success story: Global Fund grants in Burkina Faso show significantly increased absorption rates

Author:

David Garmaise

Article Type:
News

Article Number: 3

Poor absorption has been an enduring problem for grants in West and Central Africa

ABSTRACT Burkina Faso has improved the absorption rate for its Global Fund grants from 67% a few years ago to 94% as of the end of 2017. Poor absorption has been an enduring problem for many grants in West and Central Africa. A large workshop in November 2015 led to the implementation of detailed action plans to address obstacles to full absorption.

Stakeholders in Burkina Faso have succeeded in improving the absorption rate of the countryā€™s Global Fund grants. The rate has gone from 67% for the period 2012ā€“2015 to 94% as of the end of 2017.Ā Poor absorption has been a long-standing problem in all countries in West and Central Africa.

A key activity in the Burkina Faso effort was a workshop held in Ouagadougou, the capital of Burkina Faso, in November 2015, not long after the first new funding model (NFM) grants had been signed. The workshop was organized by the country coordinating mechanism (CCM). It was attended by about 100 people representing the principal recipients (PRs) and their implementing partners, technical and financial partners, the Global Fund Secretariat, the local fund agent (LFA) and the fiduciary agent. See Table 1 for a list of the grants that were active at the time.

Table 1: Burkina Faso grants for 2015ā€“2017

Comp. Name Principal recipient Budget (ā‚¬ million)
HIV BFA-H-SPCNLS Conseil National de Lutte Contre le Sida (CNLS) 29.5 m
TB/HIV BFA-C-IPC Initiative PrivƩe et Communautaire (IPC) 7.9 m
TB BFA-T-PADS Prog. dā€™Appui au DĆ©veloppement Sanitaire (PADS) 3.3 m
Malaria BFA-M-PADS PADS 59.3 m
RSSH BFA-S-PADS PADS 17.3 m
Total ā‚¬ 117.4 m

Notes:

  1. The implementation period for Burkina Fasoā€™s grants was 2015ā€“2017. All of the grants had an end date of 31 December 2017.
    2. For the 2014ā€“2016 allocation period, Burkina Faso was allotted $204.6 million. Some of this allocation was used to extend existing grants before the NFM grants were signed. This table shows the upper ceiling amounts of the NFM grants

 

The workshop was facilitated by the UNAIDS technical support facility who provided a consultant to the CCM.

Workshop participants identified obstacles, challenges, risks and bottlenecks that impede the implementation of Global Fund grants and reduce the absorption of the corresponding funds. The key programmatic challenges identified were as follows:

  • in the HIV grant, scale-up of antiretroviral therapy and the achievement of ambitious prevention targets for key populations (health care workers, men who have sex with men, and prisoners);
  • in the TB grant, the increase in the reporting rate of multi-drug-resistant TB cases;
  • in the malaria grant, the achievement of 2016 targets in vector control centered around the routine and mass distributionĀ of long-lasting insecticide-treated mosquito nets, and the scaling up of malaria diagnosis in the community; and
  • in the HSS grant, to ensure a positive impact of health systems strengthening activities on health and community staffing, and service delivery.

 

The main output of the workshop was a series of detailed action plans. A common template was used for the action plans. See Tables 2 and 3 for examples of the plans.

Table 2: Example of action plan (MDR-TB)

Target: MDR TB-2: Number of reported cases of drug-resistant tuberculosis bacteriologically confirmed (rifampicin-resistant tuberculosis and / or multidrug-resistant tuberculosis): 53 in 2014 to 136 in 2017
Obstacle 1: Delay in delivery of GeneXpert machines and cartridges
Cause: Low responsiveness of procurement agencies to PR requests for compliance with procurement plans or low flexibility in emergencies
Corrective action: Take steps to improve compliance with procurement plans and communication between procurement agencies and the PR.
Responsibility: GF and procurement agencies Finances needed? No
Start: Q1 2016 Activity already planned? No TA needed? No
Obstacle 2: Delayed installation of GeneXpert machines
Cause: Lack of an installation plan for GeneXpert machines at site level
Corrective action: Develop and implement an installation plan for GeneXpert machines at site level.
Responsibility: Programme National Tuberculose Finances needed? No
Start: Q2 2016 Activity already planned? No TA needed? Yes
Obstacle 3: Non-compliance with GeneXpert maintenance periods
Cause: Lack of a maintenance plan for GeneXpert machines at site level
Corrective action: Develop and implement a maintenance plan for GeneXpert machines at the site level.
Responsibility: Programme National Tuberculose Finances needed? No
Start: Q2 2016 Activity already planned? No TA needed? Yes

 

Jean-Thomas Nouboussi, fund portfolio manager for Burkina Faso, told Aidspan that about 30 actions were taken as a result of the workshop, covering a wide variety of areas, including governance, financial management, programmatic management and supply chain. From the 30 actions, five that were considered major were included in an Implementation Through Partnership (ITP) project that was ongoing at the time. The other 25 actions were included in Burkina Fasoā€™s grants through reprogramming.

Table 3:Ā  Example of action plan (all targets, all three PRs)

Target: All targets, all three PRs
Obstacle: Operational activities not implemented
Cause: Disbursements blocked due to insufficient (with respect to both timeliness and the quality of reports) justification of funds advanced to sub-SRs
Corrective action 1: Hold a working meeting (with the PR, the SR and the civil society platform) on the steps required for contracting with the sub-SRs.
Responsibility: Initiative PrivƩe et Communautaire Finances needed? Yes
Start: Q2 2016 Activity already planned? No TA needed? No
Corrective action 2: Initiate service contracts between SRs and sub-SRs.
Responsibility: SRs Finances needed? No
Start: Q2 2016 Activity already planned? No TA needed? No
Corrective action 3: Make the necessary revisions to the budget to allow for an effective implementation and a better follow-up and control of the contracting with the sub-SRs.
Responsibility: Initiative PrivƩe et Communautaire Finances needed? yes
Start: Q2 2016 Activity already planned? No TA needed? No

 

Table 4 provides an example of the tracking that was used forĀ the ITP-related activities.

Table 4: Example of the tracking system used for ITP-related activities

Action: Technical support for the development and implementation of a plan to install and maintain GeneXpert machines
Action type: Additional TA Disease component: TB
Partners involved: U.S. Government, WHO, Stop TB
Planned start date: 2015-11-01 Planned finish date: 2016-06-30
Actual start date: 2015-11-01 Actual finish date: 2016-06-30 (projected)
Status as of 31 March 2016: On track
Comments from partners (edited): All 12 GeneXpert machines that were ordered from GDF are ready for shipment. The country now just needs to send their importation declaration. A TA mission is scheduled for June to address, amongst other things, implementing the machines; setting up an M&E system; and assisting the country in developing a sample referral systemā€¦. We have received a notice that the machines will arrive in April. The PR and SR have been informed. They will take action to accelerate the processā€¦.

 

The ITP project came to an end in March 2017.

After the workshop, the CCM and the PRs created a committee to monitor the implementation of all 30 actions. Technical partners and the donors who sit on the CCM were represented on the committee. The committee was also responsible for working with the PRs to identify other activities that could improve absorption.

During the two-and-a-half-year duration of the grants, each PR, with the support of the country team at the Secretariat, developed annual reprogramming requests that helped to re-direct savings to relevant and, often, underfunded activities.

In addition, the Global Fund Board approved the transfer of funds from less performing grants (i.e. RSSH and TB/HIV) to the malaria grant to procure additional commodities. The transfer (ā‚¬Ā 2.6 million) was approved by the Global Fund Board in September 2017.

According to Dr Nouboussi, other activities that helped to increase absorption included the following:

  • training PRs on the 15% flexibility guidelines;
  • continuous efforts by the country team to engage the CCM, PRs and technical partners; and
  • increased coordination among PRs (a collaboration memo was signed by all PRs and the CCM).

 

With respect to the 15% flexibility guidelines, PRs have the authority to implement non-material revisions to the budget without prior approval from the Global Fund. The guidelines for grant budgeting define non-material revisions as less than a 15% change to the total budget (for standard interventions).

By the end of 2016, the absorption rate had risen to about 75%. As of 31 December 2017, which is the end date of the grants, the absorption rate was 94%.

On 1 December 2017, the Global Fund Board approved an HIV grant (ā‚¬ 32.1 million), a TB/HIV grant (ā‚¬ 7.0 million) and a malaria grant (ā‚¬ 84.6 million) for Burkina Faso. Activities related to the previous RSSH grants have been folded into the malaria grant.

Sharing the results

The results of Burkina Fasoā€™s efforts to improve absorption have been presented at the CCM and to in-county stakeholders. Three regional workshops within Burkina Faso are being organized by the CCM and networks of civil society organizations (with the participation of all implementers at decentralized levels, including community representatives) to share the results and lessons learned, and to mobilize stakeholders for successful implementation of the new grants.

The Global Fund will likely want to share this success story with other countries in West and Central Africa (or beyond).

The templates used in Tables 2ā€“4 were created by Aidspan for this article.